Jtec HCM, Inc.

PROJECT DELIVERY MODELS
HOME CONTACT
       

There are numerous ways to deliver a project. Jtec will work closely with the Owner to choose the delivery model that best fits the project's needs. These include the following:

Modified Integrated Project Delivery

  • Pros:
    • Early involvement of key participants
    • Shared risk/reward based on project outcome
    • Joint project control
    • Reduced liabilty exposure (risk)
    • BIM works well
    • Lean design & construction principles applicable
    • Early cost insight
    • Value Engineering continuous
    • Documents generated from a single BIM model for permitting, bidding, fabrication
    • Builders share knowledge and expertise when it is most valuable, in the design process
  • Cons:
    • Requires high level of trust
    • Can go awry if all parties are not willing to collaborate
    • Requires significant Owner participation; not for passive Owners
    • Requires more design time up front for contractor to provide early cost insight

CM at Risk

  • Pros:
    • Brings contractor into process earlier
    • Subcontractors bid to only one General Contractor
    • Contract agreement is expedited
  • Cons:
    • Price not known until all bids are received
    • Bid prices based on drawings/specifications
    • Ommitted scopes allowed to be added later as change order

Guaranteed Maximum Price

  • Pros:
    • Transfers risk to Contractor
    • Provides greater control over spending as the contractor is bound to a maximum price
    • Contractor can be brought in early to provide cost insight
  • Cons:
    • Price may be higher to protect Contractor
    • Scope changes tend to cost more.

Design-Build

  • Pros:
    • Portion of risk shifts to Design/Builder
    • Price and schedule known up front
    • Good for straight forward, simple projects
    • Supposed to reduce overall schedule
  • Cons:
    • Stipulated sum (price) commonly over-priced to protect D/B team
    • Designer works for contractor, no longer Owner's advocate
    • Scope altered to fit budget
    • Minimum code requirements delivered
    • Difficult with complex (Hospital) projects

Design-Bid-Build

  • Pros:
    • Owner retains control
    • Decision remains with Owner
    • Needs only one bid
    • Risk on Contractor of including all elements of design
  • Cons:
    • Actual Price is not known until bid day
    • Adversarial relationship with Contractor
    • Risk of potential claims
    • Bid based on drawings; omissions resulting in change orders
    • Deferred Approvals extend schedule
    • Do not know project team until bid
    • No say on who is on Contractor team

Copyright©2012 Jtec HCM, Inc. All rights reserved.